Aterio, an alternative data provider tracking U.S. infrastructure development, today reported that early site work has begun at SB Energy’s PORTS Technology Campus in Pike County, Ohio. Planet satellite imagery shows land clearing near the first two planned building footprints, and Ohio EPA records list two active construction stormwater permits issued on November 2 and November 4, 2026, covering 34.4 and 7.59 acres.
This press release features multimedia. View the full release here: https://www.businesswire.com/news/home/20261119625938/en/
Satellite imagery shows land clearing near the first two planned buildings at SB Energy’s PORTS Technology Campus between October 27 and November 10, 2026. (Analysis by Aterio; imagery: Planet)
Aterio estimates the first two PORTS buildings at 450 to 472 MW of IT capacity each, or roughly 900 to 944 MW combined. The range reflects an August 2026 grading plan showing 450 MW per building and SB Energy’s September 2026 SEC filing citing about 472 MW per planned building. SB Energy describes Phase 1 as about 800 MW, and OpenAI expects that initial capacity to become available in 2028, largely using existing AEP infrastructure.
Financing commitments
On November 12, SoftBank said it expects to recover $5.6 billion of its remaining $6.6 billion in power equipment advances from the PORTS-Pike generation project, with $3.4 billion in the near term and $2.2 billion by the end of 2027. SoftBank separately reported a $3.7 billion procurement loss that it said was unrelated to PORTS-Pike, and its latest earnings materials continue to show 20-year leases to OpenAI for 8.0 GW of critical IT capacity.
NVIDIA signed agreements on August 17 that cap its initial guarantee at $105 billion for about 4.25 GW of IT load, following earlier media reports of talks around a roughly $250 billion backstop. In November, NVIDIA confirmed the guarantees cover nine buildings and take effect as each is completed and ready for service, with the first expected in NVIDIA’s fiscal 2029, which begins in calendar 2028.
Permits still pending
The U.S. Army Corps of Engineers is targeting November 30, 2026 for provisional notification and January 29, 2027 for its final permit decision on the two-building federal review. Ohio EPA has closed comments on the main campus water quality application, with a final decision not yet confirmed. The separate Artemis power project has a state water quality hearing on December 30, 2026, with comments open through January 7, 2027.
What Aterio is watching next
If PORTS remains on track for first capacity in 2028, Aterio expects construction on the first two buildings to move from grading to foundation work and structural steel framing in the first half of 2027. As work advances, Aterio will refine its capacity range using the rated capacity of installed electrical and cooling equipment and confirm operating capacity once commissioning records are available.
Aterio is also tracking Ohio policy that could affect later phases of the campus. The Ohio Senate Finance Committee held its first hearing on November 17 on S.B. 374, which would prohibit new data center sales tax exemptions, and Governor-elect Amy Acton has proposed a conditional moratorium on new data centers. The tax bill could raise costs for future phases, while a moratorium could delay construction.
The full analysis, including source documentation, is available at https://www.aterio.io/blog/ports-technology-campus-dirt-is-moving.
Aterio is an independent data provider and does not hold or trade securities of SoftBank, NVIDIA or any other company named in this release. Capacity figures and construction milestones in this release are Aterio estimates based on public regulatory filings, permit records, company disclosures and satellite imagery, and are not commitments by SB Energy, OpenAI, SoftBank, NVIDIA, AEP, the U.S. Army Corps of Engineers or Ohio EPA. Actual capacity and timing could differ materially.
About Aterio
Aterio provides real-time, facility-level intelligence on U.S. data center development, power demand, and digital infrastructure growth. Its continuously updated dataset tracks active, under-construction, and announced projects for investors, energy companies, infrastructure providers, and strategic planners. Learn more at www.aterio.io.
View source version on businesswire.com: https://www.businesswire.com/news/home/20261119625938/en/
Media gallery